A-0401 L5 Weekly Construction Update 11 July 2019

Foundation process has started on Progress Way.  500 linear feet of perimeter footings were installed today.  Installation of plumbing & fire suppression sleeves installed.  This will allow an easier transition for construction rough.  Front retention basin construction is continuing as well as seeding and straw application for soil retention.