A-0401 L5 Construction Update

At the end of the week for November 15, 2019 L5 is starting to pick up the pace. Still not where we wanted to be, but getting there. Tilt panels are receiving their primer coat and elastomeric coating. The medium texture is starting it’s install this week coming. The roof is getting finalized with the stripping in of break metal and gutters. Mezzanine construction is complete and will pour on Monday, November 18th. The floor slab was removed in its entirety and will be replaced the week of 18 November. The wet cure will insure it’s final cure is impeccable. All utilities are connected at this time with roof top units setting this week coming.